Case study
Le Graham
Renovation of several departments of the residence, including cabling, with the main telecom room decommissioned without any service interruption.
- Mandate type
- Renovation while operating
- Year
- 2026
- Integrated systems
- Câblage · Réseaux & Wi-Fi
The challenge
Renovate several departments of the Le Graham residence, including removing the main telecommunications room, without interrupting service to residents.
Our approach
Zone-by-zone work planning to keep services running at all times
Progressive migration of the cabling to the new infrastructure before removing the old telecom room
Coordination with building management for access and work schedules
The outcome
Zero service interruption for residents throughout the work, including the complete relocation of the main network infrastructure.