Skip to main content

Case study

Utile St-Patrick

Project management of the technology scope plus unified network installation: Wi-Fi, access control, cameras and HVAC. Termination and testing of every network cable in the apartments.

Mandate type
New construction
Year
2026
Integrated systems
Gestion de projet · Réseaux & Wi-Fi · Contrôle d'accès · Vidéosurveillance · HVAC · Certification de câblage

The challenge

Handle project management and the full installation of the technology infrastructure of Utile St-Patrick, including terminating and testing every network cable in the apartments.

Our approach

  1. Project management of the technology components

  2. Installation of the unified network, including Wi-Fi, access control, cameras and HVAC

  3. Termination and testing of every network cable across all apartments

The outcome

The building was delivered with a fully operational unified network and cabling validated unit by unit, as part of a renewed partnership with the client Utile.